CASE STUDIES
Add Videos
Product links - Category
of work (e.g. K-rend, soda blasting, degreasing etc.)
Name and location of project: Travel Lodge,
Newport
Client details- DTZ Property Management
Location – Newport
Timescale
14
DAYS
Nature of the project- Task
The suggested improvements
To
remove all flaking paint from exterior steel cladding and redecorate
To
remove and soda blast all rusted security window grills and redecorate, and
replace grills (to reduce cost of replacing for new)
Remove
moss and unsightly and algae growth from all pathways
To
remove redecorate steel cladding in appropriate matching paint
Make
minor repairs to some exit doors and re decorate
To
enhance visual appearance
What you actually did
We
carried out a fully property survey with the client management team and
discussed the various options and approach to the job including the repairs
rather than replacement of security grills, broken glazing and doors
Task
We
hired in the specialised lift access equipment
We
carried out stripping off affected cladding using high pressure washers with
special oscillating heads to strip off old coatings.
We
then treated with steel cladding with anti-rust primers
We
soda blasted the metal grills and treated with appropriate primers and
undercoat
We
treated pathways to remove moss after treating with high pressure jet
washing
We
delivered the project to standard required by the client.
Client testimonial
“APT were engaged to carry out difficult Algae and moss staining to the travel lodge building in the centre of Newport city. They project planned and delivered exceptional results under our budget cost, will be using on other projects in the future.”
“APT were engaged to carry out difficult Algae and moss staining to the travel lodge building in the centre of Newport city. They project planned and delivered exceptional results under our budget cost, will be using on other projects in the future.”
DTZ
Property Management
Other comments.
There
were obstacles regarding constant movement of children staff and other
contractors to be considered during the working day these were overcome by implementing
a detailed but flexible approach and day to day management and school team.