Monday, 15 May 2017

Case Study Armored Auto Group cladding cleaning, renovation, soda blasting & commercial decorating

CASE STUDIES

Category of work- cladding cleaning & renovation, SODA BLASTING, AND COMMERCIAL DECORATING 

Name and location of project – cladding cleaning and restoration Ebbw vale
to carry out restoration and re decorating works to enhance the appearance and to maintain the integrity of the building under the current building lease
the refurbishment of factory storage warehouse - involving high level cleaning, soda blast cleaning, cladding repairs, cladding cleaning, algae removal commercial painting

Client details
Armored auto group

Timescale
14 DAYS

Nature of the project- Task
To remove all damaged and flaking paint from exterior steel cladding panels
Remove algae from steel cladding, all pathways
To strip paint from damaged paint coated steel cladding by soda blasting whilst cleaning cladding and remove surface rusting from selected steel panels and all rusted security window grills
carry out commercial decorating to re-coat and colour match to existing cladding 
Make minor repairs to some exit doors and re decorate to enhance visual appearance

What you did
We carried out a fully property survey with the client management team and discussed the assorted options and approach to the job including the repairs rather than replacement of steel coated cladding, security grills, damaged cladding and replace broken glazing units

Task
We hired in the specialised lift access equipment to carry out the high-level cleaning
We carried out stripping paint damaged off affected cladding using high pressure cleaning and jet washing using oscillating blast head lances .to remove the rust and old paint coatings from the metal window grills using Eco safe soda blast cleaning systems with special vortex cleaning head treated with appropriate primers and paints
the pathways and other algae covered areas and pathways were treated with algae free to remove algae and moss after treating with high pressure jet washing
We then treated with steel cladding with anti-rust primers and re decorated

We delivered the project to standard required by the client. 

Client testimonial
after discussion, the project with 5 other companies apt came were the most helpful and provided us with various alternatives which saved us thousands of pounds from alternatives allow us to spread the savings to other areas. all the work was professionally planed and exceeded expectations happy to recommend and use apt in future 

Any other comments.
There were obstacles regarding constant movement staff, visitors and other contractors to be considered during the working day these were overcome with apt delivering a detailed and flexible approach to the project

Jason Lewis - site service and facilities