Heading :
Industrial and Commercial Cleaning, Bridge Specialists
Client
: Caerphilly County Borough Council
Project: Cleaning
of Joe Calzaghe Railway and River Foot Bridge, Cwmcarn, South Wales
Client Problem
The pedestrian railway bridge had been constructed over 15 years ago and
had heavy contaminated build-up of unsightly green algae and moss. There also
crude graffiti on a painted mural that ran along the foot bridge. It was very
unsightly and the foot way had become very slippery and was affecting safe
passage for pedestrians and school children going to and from the school and village.
Situation
Caerphilly council had used us as
a specialist commercial cleaning company to successfully carry out cleaning of the
main trunk road bridge, and to remove graffiti from the roadway and railway bridge
a few years earlier, however this bridge was very complicated and had very
difficult access problems. The bridge ran
over the busy railway line and river crossing and was the main route for over
1000 children and pedestrians using the local swimming pool. To enable us to safely
remove graffiti and clean the many years
of algae staining, the commercial high level cleaning team and graffiti removal
team had arranged to carry out the work
whist the bridge remained open as this was the only access for pedestrians so safety and pedestrian management was paramount.
APT have
over 25 years of experience in commercial high level bridge cleaning and using the
specialist methodology, tools and specialist high level cleaning equipment combined
with our specialist cleaning products we put together an acceptable safe system
of works and commercial high level cleaning programme. We carried out the
project working around busy periods
with safe pedestrian and management in place. We used our rope access and high level
commercial cleaning teams for the highest points of the bridge which were over
20 meters high.
Result
A very
successful end result which exceeded the clients expectations, many great
comments received from local residents' about the improvement it made to the
overall ‘look’ of the area and safe finish of the work.
Testimonial
– Andrew and the APT team carried out a fantastic
job under difficult conditions they managed the project throughout the Joe
Calzaghe bridge again looks fantastic
– Veronica, Highway structures engineer, Caerphilly Borough Council